Days 26–27: Blocks, trenches and drainage pipes

The blocklayers waste no time in getting organised. Meanwhile Jarrod digs the trenches for the stormwater and sewer lines that connect into the sewer and stormwater mains at the south-east corner of the site.

Blocklayer and excavator 45 DSC_0883

Mixing ‘mud’ for the block walls as the excavator swings into action

Trench drainage 1 45 DSC_0851

Looking up at a newly dug trench

 

Trench drainage 2 45 DSC_0852

Standing at almost the same spot, looking across, and most importantly though a bit deceptively, down!

 

 

 

 

Drainage along boundary 45 DSC_0862

One advantage of a steep site: getting the ‘fall’ required for stormwater and sewerage drainage pipes is easy!

Drainage connections 45 DSC_0846

Connected! Stormwater and sewer drainage lines are completely separate.