Join 54 other subscribers
Recent Comments
dougacoop on Details, details: roof st… Ryan Hines on Details, details: roof st… Paul Balga on Days 93 and 94: roof on! Paul Balga on HOME MyrtleSt on Purlins, rafters and butterfly… -
Recent Posts
- Days 93 and 94: roof on! 2014/09/10
- Details, details: roof structure 2014/08/18
- Purlins, rafters and butterfly roofs 2014/07/19
- From this … to THIS 2014/07/07
- A bit of steel, a lot of wood 2014/06/02
- A bridge and a tank 2014/06/01
- Caring for trees 2014/05/22
- Interlude: Bella and the mountain dragon 2014/05/19
Archives
Meta
Daily Archives: 2014/04/23
Day 18: lucky time
Saturday: the team is driving ahead to be ready for the planned concrete pour on Tuesday. Two more carpenters join in just for the day to assist Ian and Damien. It’s a lucky time for your photographer, who works full-time and hates … Continue reading
Posted in Uncategorized
Leave a comment
Days 6–20: reo, cast-in plates and formwork
Despite some rainy days that slowed down and in a few cases temporarily stopped progress and a 4-day illness for a key building team member, things move ahead. Holes are drilled into rock in the bottom of the pier-hole excavations … Continue reading
Posted in Uncategorized
Leave a comment
Day 5: piers without peer
From today the piers are all dug. Then it’s on to digging the small strip footings that would support the block walls at the front of the house high up on the hill. Progress has been slow but steady on … Continue reading
Posted in Uncategorized
Leave a comment